Hey There! Before You Go. 😧
Get the best vintage content straight into your inbox!

Don't worry, we don't spam

Rare Historical Photos of Construction of the Tyne Bridge in Newcastle upon Tyne

The Tyne Bridge is one of North East England’s most recognizable landmarks. It spans the River Tyne, connecting Newcastle upon Tyne on the north bank to Gateshead on the south. Designed by the engineering firm Mott, Hay, and Anderson — who later went on to design the Forth Road Bridge — the structure was built by Dorman Long & Co. Ltd. Construction began in 1927, and the finished bridge was a parabolic arch design that would go on to define the skyline of both cities. These rare photographs follow the build from its earliest foundations through to the grand opening in October 1928.

View of the Tyne Bridge in the very early stages of construction, looking from Newcastle upon Tyne over towards Gateshead, March 22, 1927
View of the Tyne Bridge in the very early stages of construction, looking from Newcastle upon Tyne over towards Gateshead, March 22, 1927

By the spring of 1927, workers had broken ground and the first signs of the bridge’s footprint were visible along the riverbanks. The project was ambitious in scale — the arch would eventually stretch 531 feet across the River Tyne, making it one of the largest single-span bridges in the world at the time of its completion. Dorman Long & Co., a Middlesbrough-based steel manufacturer, was responsible for all the steelwork. They had extensive experience with large bridge contracts, and the Tyne Bridge would become one of their most celebrated projects.

Work on the Tyne Bridge arch underway. The first sections of steelwork rise over Hillgate Quay, Gateshead, August 10, 1927
Work on the Tyne Bridge arch underway. The first sections of steelwork rise over Hillgate Quay, Gateshead, August 10, 1927

Through the summer of 1927, steel sections began rising above Hillgate Quay on the Gateshead side. Workers built the arch outward from both banks simultaneously, using a system of support masts and cables to hold each steel section in place as the structure extended further over the river. This method, called cantilevering, allowed the two halves to grow toward each other without any supporting framework below — there was nothing beneath the steelwork but the river itself.

View of support mast and cables holding the Tyne Bridge in place as it is constructed, November 29, 1927
View of support mast and cables holding the Tyne Bridge in place as it is constructed, November 29, 1927

By late November 1927, the cable support system was in full operation. Tall masts anchored to the riverbanks held thick wire cables that bore the weight of the growing arch sections. The precision required was extraordinary — every new piece of steel had to be exactly positioned before being permanently riveted into place. Hundreds of riveters, crane operators, and steel erectors worked at height above the Tyne throughout the cold winter months.

View through the girders from the Gateshead side of the Tyne Bridge to the Newcastle side, January 27, 1928
View through the girders from the Gateshead side of the Tyne Bridge to the Newcastle side, January 27, 1928
View of progress with the Tyne Bridge, February 2, 1928, showing the two halves getting closer together
View of progress with the Tyne Bridge, February 2, 1928, showing the two halves getting closer together

By early February 1928, the two halves of the arch were clearly visible closing in on each other from both banks. Photographs taken on February 2nd from multiple angles show the gap shrinking rapidly. The Newcastle side and the Gateshead side were on a precise collision course, engineered to meet at a single central point above the middle of the river.

View of the Tyne Bridge from Gateshead, February 2, 1928, showing the two halves getting closer together
View of the Tyne Bridge from Gateshead, February 2, 1928, showing the two halves getting closer together
View of the Newcastle side of the Tyne Bridge captured during its construction, February 2, 1928
View of the Newcastle side of the Tyne Bridge captured during its construction, February 2, 1928

The pace of steelwork accelerated through mid-February. Each day, new sections were lifted by crane and locked into position. The bridge’s parabolic curve became more defined as the arch grew, giving workers and onlookers a clearer sense of the final shape. Photographs from February 15th and 17th show the bracing structure between the arch ribs, which was critical to keeping the geometry stable during construction.

View of the Tyne Bridge captured from the Newcastle side during its construction, February 15, 1928
View of the Tyne Bridge captured from the Newcastle side during its construction, February 15, 1928
Bracing between the Tyne Bridge arches, February 17, 1928
Bracing between the Tyne Bridge arches, February 17, 1928

February 23, 1928 was the most significant single day of the entire construction project. That day, the final central girder was lowered into place, and the two halves of the arch met above the River Tyne. It was a moment that workers had spent nearly a year building toward. To mark the occasion, steel erectors, riveters, and crane drivers climbed up onto a 20-ton capacity crane and posed for a photograph — a fitting way to celebrate what they had built with their own hands.

The Tyne Bridge arch is nearly complete as a girder is lowered into place above the River Tyne, February 23, 1928
The Tyne Bridge arch is nearly complete as a girder is lowered into place above the River Tyne, February 23, 1928
An historic moment as the Newcastle and Gateshead sides of the Tyne Bridge meet, February 23, 1928
An historic moment as the Newcastle and Gateshead sides of the Tyne Bridge meet, February 23, 1928
Steel erectors, riveters and crane drivers perch on a 20-ton capacity crane to mark the completion of the Tyne Bridge arch, February 23, 1928
Steel erectors, riveters and crane drivers perch on a 20-ton capacity crane to mark the completion of the Tyne Bridge arch, February 23, 1928

Four days later, flags were flown above the completed arch to celebrate the milestone. The arch itself was finished, but a great deal of work remained. The roadway still needed to be laid, the towers required continued construction, and all the finishing details had to be completed before the bridge could open to the public. The construction staff — employed by Dorman Long & Co. — gathered for a group photograph on March 2nd, a record of the workforce that had made it all possible.

Flags fly above the Tyne Bridge to celebrate the completion of its arch, February 27, 1928
Flags fly above the Tyne Bridge to celebrate the completion of its arch, February 27, 1928
Construction staff of the Tyne bridge, employed by Dorman Long & Co. Ltd, March 2, 1928
Construction staff of the Tyne bridge, employed by Dorman Long & Co. Ltd, March 2, 1928

Through March 1928, photographs taken from various vantage points — including from the older High Level Bridge nearby — show the Tyne Bridge in its full arch form, still surrounded by cranes and scaffolding. The towers at each end were built from Cornish granite and designed by local architect Robert Burns Dick. They were originally intended to function as warehouses, with five floors of storage space inside. However, the interior floors were never completed, so the storage areas were never actually used. The North Tower did have a working lift that gave passengers and goods access to the Quayside below, while the South Tower had a lift shaft but no lift was ever installed.

View along the Tyne Bridge looking towards Newcastle, as work on its construction continues, March 6, 1928
View along the Tyne Bridge looking towards Newcastle, as work on its construction continues, March 6, 1928
View of the Tyne Bridge from Gateshead, as work on its construction continues, March 6, 1928
View of the Tyne Bridge from Gateshead, as work on its construction continues, March 6, 1928
View of the Tyne Bridge from the High Level Bridge, March 6, 1928
View of the Tyne Bridge from the High Level Bridge, March 6, 1928

By May 1928, attention had shifted to the roadway. Workers laid the surface that would eventually carry traffic between Newcastle and Gateshead. Photos from May 18th and 22nd show crews progressing steadily along the bridge deck, with the completed arch overhead and the river far below.

View along the Tyne Bridge as work on its roadway continues, May 18, 1928
View along the Tyne Bridge as work on its roadway continues, May 18, 1928
View along the Tyne Bridge towards Newcastle, as work continues on its roadway, May 22, 1928
View along the Tyne Bridge towards Newcastle, as work continues on its roadway, May 22, 1928

Into September 1928, the granite towers were nearing their final form. Photographs from September 6th and 19th show scaffolding still wrapped around the towers as stonemasons finished the upper sections. By late September, the roadway was nearly complete and the bridge was beginning to look exactly as it would on opening day.

View of the Tyne Bridge towers under construction, September 6, 1928
View of the Tyne Bridge towers under construction, September 6, 1928
View of the Tyne Bridge towers under construction, September 19, 1928
View of the Tyne Bridge towers under construction, September 19, 1928
View of the Tyne Bridge roadway nearing completion, September 25, 1928
View of the Tyne Bridge roadway nearing completion, September 25, 1928
View along the Tyne Bridge as it nears completion,, September 25, 1928
View along the Tyne Bridge as it nears completion,, September 25, 1928

The bridge was officially completed on February 25, 1928 — meaning the arch was structurally finished — but the opening ceremony did not take place until October 10, 1928. King George V and Queen Mary arrived in their Ascot Landau carriage and became the first people to officially cross the bridge. Twenty thousand schoolchildren were given the day off school to attend the ceremony. Movietone News captured the King’s speech on film. By the time this photograph was taken on October 1st, just days before the opening, the Tyne Bridge stood ready.

View of the Tyne Bridge, October 1, 1928
View of the Tyne Bridge, October 1, 1928
Enjoyed this post? Get new ones in your inbox.

1 thought on “Rare Historical Photos of Construction of the Tyne Bridge in Newcastle upon Tyne”

Leave a Comment

Your email address will not be published. Required fields are marked *

Share this Post 🥺

Please take a moment to share this content. Your support is greatly appreciated! 🙌🙏

Share this Post 🥺

Please take a moment to share this content. Your support is greatly appreciated! 🙌🙏
Scroll to Top
 
Hey Friend, Before You Go.. Please like & follow for more interesting content